Moses Mabhida stadium on track: Management

Posted On Wednesday, 07 November 2007 02:00 Published by eProp Commercial Property News
Rate this item
(0 votes)

Construction on the Moses Mabhida 2010 Soccer World Cup stadium is on track

2010Construction on the Moses Mabhida 2010 Soccer World Cup stadium is on track and the delivery of the stadium is not in jeopardy, Group Five-WBHO Consortium said on Wednesday, hours after thousands of workers downed tools.

More than a thousand disgruntled construction workers downed tools at 7am on Wednesday and began toyi-toying at the stadium after talks with management failed on Tuesday.

KwaZuluNatal regional organiser and chief negotiator for the National Union of Mineworkers (NUM), Msi Poswa, said no agreement had been reached after eleven hours of talks with management.

"We wasted our time. We were locked in negotiations from 10am yesterday (Tuesday) until 9pm," Poswa said.

Group Five's Heidi Geldenhuys said on Wednesday that NUM had tabled an "unrealistic demand for an across the board payment to workers".

She said management refused to entertain the demands in view of the "centrally negotiated three year agreement covering terms and conditions of employment".

"The union elected to walk out of negotiations on Tuesday night even?though differences were not irreconcilable and despite management's commitment to continue talking on Wednesday morning," she said.

NUM is demanding project bonuses of R1,500 a month for each worker.

Initially, R9 an hour had been demanded.

Last week NUM said it was demanding project bonuses of R1,200 a month, but Poswa said the union had "reverted back to R1,500 because management has not moved at all".

It is also demanding that subcontractors meet minimum wage requirements for the civil engineering sector.

Last week, NUM regional co-ordinator Bonginkosi Mncwabe said: "They (the consortium) agreed to it, but what about all the time they (the workers) have worked so far? There must be back pay."

However, on Monday Craig Jessop, Group 5's KwaZulu-Natal managing director, said that not all the subcontracting firms fell under the sectoral wage determination for the SA Federation of Engineering Contractors (Safec).

The union is also demanding that workers be allowed to elect a full-time safety compliance worker as they are unhappy with the 15 safety compliance officers provided by the consortium.

Despite the union's complaints about safety, the Mercury newspaper on Tuesday reported that the R2.5 billion Moses Mabhida Stadium had "scooped an industry award at the weekend for the safest building site in KwaZulu-Natal".

The construction site scored more than 90% in the Master Builders' Association Awards for safety in projects valued at more than? R500-million.

By 2pm on Wednesday, Poswa said hundreds of workers were still toyi-toying at the stadium.

 

Last modified on Saturday, 02 November 2013 10:01

Most Popular

GMI Property Group adds a New Mall to its Stable: Bronkhorstspruit Mall

Jul 21, 2022
GMI Properties Group announces the development of the much-anticipated Bronkhorstspruit…

Equites Property Fund and Mabel conclude B-BBEE transaction

Jul 21, 2022
Andrea Taverna-Turisan
The JSE listed specialist logistics property fund, Equites, today officially announced…

Broad commercial property market softening expected due to ongoing and more rapid rate of interest rate hiking

Jul 21, 2022
Default Image
The still-bigger 75 basis point hike announced this afternoon, after the previous 125…

The rapidly rising cost of living is reflecting in residential rentals

Jul 21, 2022
TPN Graph-Rental Demand
Demand for residential rental properties saw some recovery in the first quarter of 2022…

Sky City Mall: We’re expecting our horizons in 2022

Jul 21, 2022
We’re moving forward with changes driven by the convergence of pandemic and longstanding…

Please publish modules in offcanvas position.